Seismic Program
1936 West 10 Avenue Vancouver, BC V6J 2B2
Google map of Tennyson Elementary
To see a detailed timeline of the seismic process, please click here.
Current Status
- The construction of the new school is completed. The occupancy of the new school was achieved on December 3, 2020. School is now occupied.
Next Steps
- Old building will be demolished and a new play field will be put in place. Hazmat demolition will commence this winter.
Contact Information
- Parents and staff may direct questions to their principal
- The principal is a member of the seismic Project Team