www

Maquinna Elementary

SEISMIC PROGRAM

2684 East 2nd AVE, Vancouver, BC V5M 1C9

Google Map of Maquinna Elementary


To see a detailed timeline of the seismic process, please click here.

Current Status

  • Project Design
    • Designing of the seismic upgrade of the school.
    • Preparing drawings and specifications for permitting from the City of Vancouver and for procuring construction contracts. 
    • Funding approval announcement, April 25th, 2019.
    • A public information session was held on Tuesday, May 28th from 3:00pm to 6:30pm in the Maquinna Gymnasium. 
    • The display boards can be viewed here.
    • General information about this project can be found on the project Factsheet.
    • Feedback was be collected for two weeks following the public information session.

Next Steps

  • Approval of construction (pre-tender) budget by the Ministry of Education.

Temporary Accommodation

  • Temporary accommodation is being planned for students at Seymour Elementary.

Contact Information

  • Parents and staff may direct questions to their principal
    • The principal is a member of the seismic Project Team

 