Current Status

  • Project Design
    • Designing of the seismic upgrade of the school.
    • Preparing drawings and specifications for permitting from the City of Vancouver and for procuring construction contracts. 
    • Funding approval announcement, February 11, 2019
    • A public information session was held on Tuesday, April 2nd, 2019 from 3:30pm to 6:30pm in the Selkirk Gymnasium.
    • Additional information regarding the planned seismic upgrade can be found on this fact sheet
    • Display boards from the public information session can be found here.
    • Feedback forms can be completed here. Feedback will be collected for two weeks following the public information session.

Next Steps

  • Approval of construction (pre-tender) budget by the Ministry of Education.

Temporary Accommodation

  • Temporary accommodation is being planned for students in grades 6 and 7 at Gladstone Secondary. Students in Kindergarten through grade 5 will remain at the school during construction.